On May 2, 2022, the Brandon City Council voted unanimously to move forward with a water treatment plant expansion project to meet the City’s future needs. Additionally, the City Council voted unanimously to incorporate reverse osmosis treatment technology into the project to address water hardness levels.
Project Schedule:
Water Treatment Plant Facilities Plan - Completed March 2021
Design of the Water Treatment Plant - Completed in 2022
Construction - Starting July 2022
Tentative Construction Completion - End of 2024
Design of the Water Treatment Plant - Completed in 2022
Construction - Starting July 2022
Tentative Construction Completion - End of 2024
.png)